Massachusetts ratepayers to pay extra $512M for transmission line for Canadian hydropower

3 Massachusetts energies and Main Maine Power’s moms and dad firm have actually concurred that Massachusetts ratepayers have to carry $512 million in added prices triggered by hold-ups in building of a power transmission job in Maine that will certainly permit Canadian hydropower to get to the New England power grid.